Section 3
SECTION 3: Route 130 to the Arnold Palmer
Regional Airport

PennDOT Project Name: TBD

ABOUT THE PROJECT
Section 3 extends approximately 2.5 miles from the Route 2023 and Route 130 intersection in Unity Township to the terminus of PennDOT’s Route 981 Section V10 improvement project (currently under construction) near the Westmoreland County Airpark and Arnold Palmer Airport. Section V10 includes improvements along Route 981 from the Airport to Route 30. Section 3 follows Route 2023 to just north of the Green Street intersection where it goes off alignment toward the Westmoreland Airpark. Near the Airpark, Section 3 will reconnect with Route 981 near the Section V10 Southern project limits.

ANTICIPATED* SCHEDULE
Preliminary Engineering/Environmental Approval:
2019 to Mid-2020

Final Design, Right-of-Way and Utilities:
Mid-2020 to Mid-2022

Construction:
Mid-2022 to Late-2023

* Schedule subject to change due to funding availability